Projects

Ongoing & Future Projects

Mahagenco is implementing capacity additions programmes of about 9320 MW. Project execution works of 3230 MW are in full swing and 6090 MW projects are in advanced stages of planning.

Mahagenco is aware of next green power scenario of power generation from non conventional energy resources and have clear vision for Green Power for the consumers of Maharashtra. Accordingly to fulfill Renewable Power obligation of distribution companies in Maharashtra, Mahagenco has commisioned 130 MWp Solar Power Projects till date. Mahagenco aspires to increase its solar portfolio from current 130 MWp to 450 MWp by end of the year 2015-16.

Mahagenco is implementing R&M work of 210 MW unit at Koradi. Feasibility study for implementation of R&M work at Chandrapur, Koradi, Bhusawal, Parli & Nasik is also being carried out.

MAHAGENCO’S CAPACITY ADDITION PROGRAMME

A. COMPLETED PROJECTS (2500 MW): Capacity Added in 11th Plan (2007-2012)

Name of the Project
Unit No.
Unit Capacity (MW)
Zero Date
Date of Full Load/COD
Cap. Addition During YearYear of Commisioning
Parli TPS625014.01.2004
19.05.2005 / 01.11.2007500 MW2007-2008
Paras TPS
325025.05.200410.03.2008 / 31.03.2008
Parli TPS
725031.08.200610.02.2010 / 31.07.2010500 MW2009-2010
Paras TPS
425023.01.200727.03.2010 / 31.08.2010
Khaperkheda TPS Expansion Project
550001.11.2007
05.08.2011 / 16.04.2012500 MW2011-2012  
Bhusawal TPS Expansion Project
450023.01.2007
07.03.2012 / 16.11.20121000 MW
Bhusawal TPS Expansion Project
550023.01.2007
30.03.2012 / 03.01.2014
Total2500

 B.   ONGOING PROJECTS (3230 MW): Capacity Addition in 12th Plan (2012-2017)

Name of the Project
Unit No.
Unit Capacity (MW)
Zero Date
Commisioning Date
Present Status
Cap. Addition During Year
Year of Commisioning

Koradi TPS
866023.09.2009Expected by March 2015
Boiler Light-up:11.09.20141160  MW2014-2015
Chandrapur TPS
850009.02.2009Expected by March 2015
Oil Flushing Completed- 09.08.2014
Parli TPS
825020.01.2009Expected by April 2015
Hydraulic Test (D)- 25.12.2012
2070  MW2015.2016  
Chandrapur TPS
950009.02.2009Expected by June 2015
Condensor & TG Erection Started: 14.11.2013

Koradi TPS
966023.09.2009Expected by August 2015
TG Box-up: 28.07.2014 

Koradi TPS
1066023.09.2009Expected by December 2015
Hydraulic Test- 05.07.2014

 Total3230

C.   FUTURE PROJECTS: Capacity Addition in 13th Plan (2017-2022)

Name of Project
Capacity in MW
Commisioning Year
Present Status

Bhusawal Unit 6
1 x 6602018-2019Bid submitted againt tender on EPC carried out on 13.01.2014. After scrutiny of Technical and Commercial bids, order shall be placed on the successful bidder.

Paras Unit 5
1 x 2502018-2019Land acquired – 110.92 H

MOEF TOR Received – 07.09.2012

Nasik Unit 6 (Replacement)
1 x 6602019-2020Engineering & Tender preparation in process. The Public Hearing is conducted successfully on 07.05.2013.

Correspondence for getting final EC is in process.   


Dondaicha Project
5 x 6602020-2021 to 2022-2023Land acquisition is in progress (515.86 H land acquired).

Correspondence for getting final EC is in process.

 Uran GTPS

Block-I: 406
Block-II: 814
2019-2020*Tender for Lumpsum turnkey contract for installation of 1220 MW advance class gas turbine based CCPP cancelled in view of CEA’s circular dt. 19.03.2012 in respect of non-availability of domestic gas for the gas based projects and advised not to plan gas based project till 2015-2016.

 Subject to availabilty of gas.

 D. SOLAR PROJECTS:

To fulfill Renewable Power Obligation of Mahadiscom, Mahagenco has planned to setup the Solar Power Projects in Mahrashtra.

FINANCIAL YEAR

Target MW Capacity
as per SOLAR RPO
Fulfilment by
Mahagenco (MWp)
Details of Solar Project

COMPLETED PROJECTS:

2010-2011118  (0.25%)11 MWp (April 2010)
CSTPS, Chandrapur
130 MWp
2011-2012 129  (0.25%)52 MWp (Oct 2011) &
2MWp (Feb 2012)
CSTPS, Chandrapur

2012-2013142  (0.25%)130125 MWp (March 2013)
Sakhari, Dist. Dhule

ONGOING PROJECTS:    

2014-2015344  (0.5%)18036+14 MWp (March 2015)
Shirsuphal Baramati through PPP
50 MWp
FUTURE PROJECTS:     

2015-2016379  (0.5%)45050 MWp – Kaudgaon, (Phase-I)
25 MWp – Sakhari, Dhule
(PPP bidding for above Projects are in progress)
50 MWp – Kaudgaon, (Phase-II)
50 MWp – Gangakhed
80 MWp – Mangladevi, Yawatmal
15 MWp – Aanterveli, Parbhani
270 MWp

E.  RENOVATION & MODERNIZATION (R&M) OF OLD UNITS TO IMPROVEMENT PERFORMANCE:

StationProject Title

 Project Start Date
Project Completion Date
Cost of Project (in Crores)

Koradi
India: Coal Fired Generation Rehabilitation on Project Koradi Unit-6 (210 MW)
March-2014Sept-2016
486